Museo del Westside
Phase Two
Design Phase - 12 weeks
Discovery/ Kick-off
.5 weeks
June 23
Initial design concepts for all 3 sections
4–6 weeks |
June 23 - August 1
Client review period (3-5 business days) |
1 week |
August 8
Revisions (3 rounds, 3–5 days each) |
|
September 5
Final file prep / production |
1–1.5 weeks |
September 12
Print and Installation Phase - 4 weeks
Send to print
.5 weeks
September 12 - 14
Print production
2 weeks
September 15 -26
Installation
2 weeks
September 29- October 10